Our achievements.
Completed development activities of Kushtia Road Department
A) Kushtia city bypass road construction project Under the project, construction work of 8.60 km road, 1 bridge, 1 railway overpass and 22 culverts have been completed.
B) Development works completed under District Road Development Project (Khulna Zone):
* The Sadarpur Bazar-Halsa Rail Bazar (Z-6465) road has been upgraded to a proper standard with 15.75 km of road widening.
* Sadarpur-Jhutiadanga-Asannagar-Hatboalia (Z-7464) road has been upgraded to 16.00 km and upgraded to proper standard.
* Daulatpur-Daulatkhali-Mathurapur High School Bazar (Z-8412) road has been upgraded to 12.30 km with proper quality.
* Bheramara-Daulatpur (Z-6411) road 20.54 km has been properly repaired.
C) Development works completed under Regional Highway Upgradation Project (Khulna Zone) at appropriate standards and width:
* Ahladipur-Rajbari-Pangsha-Kumarkhali-Kushtia (Chowdhury) (R-610) Regional Highway has been upgraded to 26.054 km.
* Charaikol-Shilaidaha (R-613) Regional Highway has been upgraded to 5.435 km. Works completed under.
PMP-Road (Major) Program: 20.54 km DBST work on :
* Bheramara-Daulatpur (Z-6411) road has been completed. Development works completed under.
PMP-Bridge / Calvert (Major) Program:
* Construction work of 13.54 m Kakiladaha bridge on Sadarpur Bazar-Halsa Rail Bazar (Z-6465) road.
* Construction work of 25.64 m Jhutiadanga bridge on Sadarpur-Jhutiadanga-Asannagar-Hatboalia (Z-7464) road has been completed.
* Besides, 16 culverts of 46.00 meters have been constructed on different district highways.
Ongoing / Implemented Development Projects (ADP):
D) Upgradation of Kushtia urban part of Jhenaidah-Kushtia-Pakshi-Dashuria National Highway (N-604) to 4-lane and proper restoration project.
* DPP Price: Rs. 56416.95 lakhs
* Implementation period: 01 January 2020 to 31 December 2022.
* Date of approval by ECNEC: 10/12/2019.
* Total number of packages in the project: 5.
* Current financial year allocation: Rs. 4000.00 lakhs.
* Current financial year expenditure: Cumulative Financial Progress: Rs. 4640.00 lakhs.
E) Upgradation project of Kushtia (Trimohani) -Meherpur-Chuadanga-Jhenaidah (R-845) Regional Highway from Kushtia to Meherpur at appropriate quality and width:
* Length of the project (Kushtia Road Division): 23.179 km.
* DPP Value (Approved Kushtia Roads Division): Rs. 30666.47 lakhs (Approved by ECNEC on 01/08/2021)
* Implementation period (Approved): 01-07-2021 to 31-12-2023.
* Length of work (km): 6.40 km.
* Estimated value: 7080.95 lakhs.
* Tender is in process.
Planning and Implementation: Cabinet Division, A2I, BCC, DoICT and BASIS