Our achievements.

Completed development activities of Kushtia Road Department

A) Kushtia city bypass road construction project Under the project, construction work of 8.60 km road, 1 bridge, 1 railway overpass and 22 culverts have been completed.

B) Development works completed under District Road Development Project (Khulna Zone):

* The Sadarpur Bazar-Halsa Rail Bazar (Z-6465) road has been upgraded to a proper standard with 15.75 km of road widening.

* Sadarpur-Jhutiadanga-Asannagar-Hatboalia (Z-7464) road has been upgraded to 16.00 km and upgraded to proper standard.

* Daulatpur-Daulatkhali-Mathurapur High School Bazar (Z-8412) road has been upgraded to 12.30 km with proper quality.

* Bheramara-Daulatpur (Z-6411) road 20.54 km has been properly repaired.

C) Development works completed under Regional Highway Upgradation Project (Khulna Zone) at appropriate standards and width:

* Ahladipur-Rajbari-Pangsha-Kumarkhali-Kushtia (Chowdhury) (R-610) Regional Highway has been upgraded to 26.054 km.

* Charaikol-Shilaidaha (R-613) Regional Highway has been upgraded to 5.435 km. Works completed under.

PMP-Road (Major) Program: 20.54 km DBST work on : 

* Bheramara-Daulatpur (Z-6411) road has been completed. Development works completed under.

PMP-Bridge / Calvert (Major) Program:

* Construction work of 13.54 m Kakiladaha bridge on Sadarpur Bazar-Halsa Rail Bazar (Z-6465) road.

* Construction work of 25.64 m Jhutiadanga bridge on Sadarpur-Jhutiadanga-Asannagar-Hatboalia (Z-7464) road has been completed.

* Besides, 16 culverts of 46.00 meters have been constructed on different district highways.

Ongoing / Implemented Development Projects (ADP):

D) Upgradation of Kushtia urban part of Jhenaidah-Kushtia-Pakshi-Dashuria National Highway (N-604) to 4-lane and proper restoration project.

* DPP Price: Rs. 56416.95 lakhs

* Implementation period: 01 January 2020 to 31 December 2022.

* Date of approval by ECNEC: 10/12/2019.

* Total number of packages in the project: 5.

* Current financial year allocation: Rs. 4000.00 lakhs.

* Current financial year expenditure: Cumulative Financial Progress: Rs. 4640.00 lakhs.

E) Upgradation project of Kushtia (Trimohani) -Meherpur-Chuadanga-Jhenaidah (R-845) Regional Highway from Kushtia to Meherpur at appropriate quality and width:

* Length of the project (Kushtia Road Division): 23.179 km.

* DPP Value (Approved Kushtia Roads Division): Rs. 30666.47 lakhs (Approved by ECNEC on 01/08/2021)

* Implementation period (Approved): 01-07-2021 to 31-12-2023.

* Length of work (km): 6.40 km.

* Estimated value: 7080.95 lakhs.

* Tender is in process.