Project Name: Residual Upgrading Project of Jhenaidah-Kushtia-Pakshi-Dashuria National Highway (N-704) along with upgradation of Kushtia town section to 4-lane.
Name of Project Manager : Executive Engineer, RHD, Roads Department, Kushtia. Duration : From 01/01/2020 to 30/06/2024.
1. DPP Price Original : 57416.95
2. Date of Approval in Ecnec Meeting : 10/12/2019
3. Date of Administrative Approval : 25/02/2020
4. Number of packages: 5
5. Current Year Allocation : 10000.00 Lakhs
6. Exemption : 2500.00 Lakhs
7. Expenditure: 467.87 lakhs
01. Kushtia Name: Che: Widening, Strengthening, DBS Base Course, Waring Course, Hard Solder Construction, RCC Box Culvert Construction, Bus Bay, Median, Side Road Development and Other Ancillary Works in Market Sections from 21+575 to 34+600.No: WD-01 Length: 13.025 KM: 05/04/2021 31/12/2022 7175.15 7160.26 100.00% 100.00% Zahirul Ltd. Work Completed
02. Kushtia Name: Che: Widening, Strengthening, DBS Base Course, Waring Course, Construction of Hardsolder, Construction of RCC Box Culvert and Side Road Development in Market Sections from Che: 34+600 to 41+000 and other ancillary works. Number: WD-02; Length: 6.40 KM: 10/11/2020 09/11/2022 3531.62 3525.54 100.00% 100.00% Rana Builders Pvt Ltd Work Completed
03. Kushtia Name: Ch: 41+000 to 46+000 Widening of Existing Pavement, Strengthening, DBS Base Course, Waring Course, Hard Solder, Construction of RCC Box Culvert, U Drain, Construction of Cover/Slab over Existing Drain, Construction of Footpath, Construction of Road Divider etc. ancillary work. Number: WD-03; Length: 5.00 KM: 04/11/2020 31/07/2023 14125.78 11436.53 82.00% 80.96% Zahirul Ltd. Work in progress
04. Kushtia Name: CH 46+000 to 51+000 Widening of existing pavement, reconstruction, DBS base course, wearing course, hard solder, construction of RCC box culvert, side road development, U drain, footpath construction, construction of road divider and other ancillary works including intersection development. . Number: WD-04; Length: 5.00 KM: 17/11/2020 31/08/2023 14785.85 9479.82 71.00% 64.11% Spectra Engineers Ltd. Work in progress
05. Kushtia Name: Widening, Reconstruction, DBS Base Course, Waring Course, Hard Solder Construction, Side Road Development, U Drain, Bus Bay, Road Divider, Median Pavement Construction, Road Divider Construction in Market Sections from Ch 51+000 to 62+800. Number: WD-05; Length: 11.80 KM: 26/10/2021 25/10/2023 14724.34 4705.25 35.00% 31.96% M. M. Builders and Engineers Ltd. Work in progress
Project Name
|
: | Upgradation of Kushtia (Trimohani)-Meherpur-Chuadanga-Jhenaidah (R-745) Regional Highway from Kushtia to Meherpur to proper standard and width.
|
Name of Project Manager
|
: | Superintending Engineer, RHD, Road Circle, Kushtia.
|
Duration
|
: | 01/07/2021 to 31/12/2023
|
1. | DPP Price
|
Core
|
: | 30666.47 lakhs | 4. | Package number : | 3 |
|
|
Amended
|
: |
|
5. | Current year allocation : | 403.87 lakhs
|
2. | Date of approval at Eknek meeting
|
|
: | 29/08/2021 | 6. | Discount : | 403.87 lakhs
|
3. | Date of Administrative Approval
|
|
: | 07/09/2021 | 7. | Expenditure : | 403.87 lakhs
|
Package Name, Number & Length Date of Issue of Work Order Date of Completion of Work Contract Price Cost (up to date of issue of report) Progress Name of Contractor Organization Remarks Physical (%) Financial (%) 01. Widening, Strengthening, Construction of Hard Shoulder and Surfacing work from Ch. 00+600 to 7+000 along with construction of 6 Nos RCC box culvert & 1 Nos PC Girder Bridge of Kushtia (Trimohoni)-Meherpur-Chuadanga-Jhinaidah Road (R-745) under Road Division Kushtia during the year 2021-2022 30/03/2023 29/03/2025 6723.10 - 3.00% - Rana Builders (Pvt) Ltd. Work in progress.
02. Widening, Strengthening, Construction of Hard Shoulder and Surfacing work from Ch 07+000 to14+000 along with Construction of 07 Nos RCC Box Culvert and 01 no of PC Girder Bridge of Kushtia-(Trimohoni)-Meherpur -Chuadanga-Jhenaidah Road (R -745) under Road Division, Kushtia during the year 2021-2022. 12/08/2022 11/08/2024 7234.07 - 6.00% - Zahirul Limited Work in progress.
03. Widening, Strengthening, Construction of Hard shoulder and Surfacing work from Ch.14+000 (Kochubaria) to Ch 23+779 (Khalishakundi) along with construction of 121.712m Long PC Girder Bridge and 31.00m RCC box culvert of Kushtia (Trimohoni)- Meherpur-Chuadanga-Jhinaidah Road (R-745), under Road Division Kushtia during the year 2021-2022. 24/07/2022 23/07/2024 9747.70 1045.99 14.00% 10.73% M/s Janmabhoomi Builders, Ohiduzzaman Chowdhury & The Niritti (John) JV work in progress.
Planning and Implementation: Cabinet Division, A2I, BCC, DoICT and BASIS